Thursday, June 6, 2013

Thursday?

Now we did get some heavy rain last night but it didn't last super long. Sure it felt nice knowing I didn't have the roof off my house. Rain's around today so crew ain't coming. Just means more time for plumbing I guess.

Lou finished his service stuff and electrical inspector signed off on his work. We'd set up Georgia Power to come first thing this morning and switch over the service. For about an hour power was off but now we have a sparkly new service.


Meanwhile, Mike did his best to measure where walls would be and ran his plumbing. He set up everything so that we could call for a rough plumbing inspection Friday. Something's getting done.

Finding Mr., or Mrs., Right

The Building Permit process has its own issues. Thought I'd play the innocent idiot - which I usually am - and head down to Buildings office and ask how to make the permit process as smooth as possible.

Triage is what they call it. They took me and my 8.5x11 plans and got me started. An hour or so later, I was in the system just waiting for Variance approval. Someone looked at my plans then came out and redlined everything that was a flag for them. With this info I could go back to Architect Allyson and she could refine the plans for submission.

Sounded easy enough. So I went ahead and planned my start date as Monday, June 3. Painting Plus signed on for demo, framing, and roofing. Got excited that we might actually begin and see how things would work out.

Problem is that once changes were made and plans (four 18x24 sets) were submitted, a different plan checker could come into the picture. And mine's name was Bistra. A nice enough Eastern European bred woman, with a biting sense of humor, but she had a different take on my plans, so triage wasn't much help.

She redlined a whole different set of things. So I sat there demoralized realizing that I knew not how I would get these changed again or how this would impact my plans. This was on Thursday morning before my Monday start date. Fortunately, the changes she wanted done were waaay superficial and had very little to do with the structure being built. It was more style over substance.

My wonderful friend, Sally, let me use her computer to make the alterations. After about 4 hours I was done. I sent the plans to FedEx/Kinko's and to print two copies (these 18x24 sets of 20 pages are not cheap). Next morning I would take them down to Trinity Avenue first thing. Hopefully, Bistra would see my revisions and give me a thumbs up.

Wednesday, June 5, 2013

Ok, Wednesday will get things going

So no rain Tuesday either - at least for us. Bright and early I get a call from Tony saying that due to a miscommunication the crew is double-booked and won't be here. They'll plan on coming Thursday. Frustration starts to set in but I see now how things run in homebuilding.

Meanwhile, I keep getting more deliveries from STOCK supply because they want all materials on site so they don't have to wait for supplies. Just about every inch of my front yard is covered in lumber covered in plastic - in case it rains.



Fortunately, Lou is still making progress with the electrical. Mike decided to come in and start a plumbing plan. He wants to go up from the basement through the back of our bedroom closet to get vents/supplies up to the second floor. So I'll take out the plaster to make room for them to run plumbing and electrical. Tomorrow should be interesting.

Tuesday, June 4, 2013

So Tuesday it is?

No rain Monday, of course. Now Tuesday is forecasted for rain. Family heads out for Lake Lanier and I get a phone call saying they're going to delay again - just in case. First thing Wednesday, they'll be here to start demolition.

Meanwhile I've pulled up all the planks in the attic with Deacon's help and had the old insulation sucked out
by the insulation company. Also, Lou Edy (electrician) has set up a new electrical service from the street and
converted our old fuse box into a 20 amp circuit breaker box. He just needs to get a few things done for the inspector to sign off. Then Georgia Power will come out and switch over to the new service.

Plan was to have 2x10s (required for plumbing by code) sistered up with existing 2x8s to create the new
floor joists. Key here is getting those floor joists in so that Lou and Plumber Mike Reynolds can then run their trades. After electrical and plumbing is set, then they can put down decking and start framing walls and raising the ridge.

Monday, June 3, 2013

D-Day is when?

So tree's still not done - down but not gone. Hoping they'd be out of the way before construction begins.
Had the dumpster delivered on Friday so we'd be ready for Monday morning start. 30% chance of rain on Monday but team wants to come rip off the roof. Should be interesting.

Family night before beginning was spent watching Young Frankenstein. Wife, kids, and Spot should take off in the morning for Lake Lanier & Close Quarters to avoid the chaos.

As the sun rose, rain chances were higher. So Tony & foreman Dieter came down and said they wanted to wait until Tuesday. I had suggested them not removing the roof but cutting the roof about 4 feet from the gutters and then framing 2x10s through those openings. That would keep majority of roof intact in case heavy rains came. They thought it better to wait until Tuesday instead of complicating demo.

So they introduced me to the demo/framing/roofing lead, Pedro, and then spent an hour or so walking him through the plans. Disappointed? Sure. One day delay isn't the end of the world though. Tuesday the 4th will work.

Friday, May 31, 2013

GOT IT! Let the Chaos Begin!!

Got there Friday morning first thing hoping to drop off my plans for Bistra. She actually showed up and told me to lay out the plans so she could see the changes. After a couple of hours, plans were reviewed and I was just waiting for the next step.

Bistra appeared out of the back and said, "Let's go." She took me over to another counter where I received my final stamped plans and building permit invoice. Took it downstairs, paid for the permit, and returned with receipt. Done! Called contractor and said we were ready to start Monday. Relief at last - even if it is still "at risk".


Permitting Deeper? Or just crazier?

So here's how it went down for getting the At Risk Permit. You have to be on the docket for a BZA meeting to secure your variance. With that date in hand, you then sign a letter saying that you want an At Risk Permit and drop it to the City Building folks. One catch: IF you don't get your variance from BZA, any work you have performed must be demolished within 30 days. Big IF huh?

For me, I didn't see the downside in At Risk. There were no grounds to be denied, so I figured this whole BZA thing was just a formality. Real downside was waiting an extra month and then having the house in shambles while Wendy is going mental preparing for school to start. No competition on what I should do.

Plan was to charge forward with plans and go to the June 6 BZA for variance approval. That meant my real focus needed to be getting the architectural plans finalized, with structural engineer's letter, to get my At Risk Permit. Sound crazy? I'm sure many thought so.